Track Renovation Page
Renovation Progress Spring-Summer 2008
Scope of the Work:
- Removal of rubberized surface and inspection of the bituminous concrete surface below.
- Repair of Bituminous Concrete (if necessary) and resurfacing of the track with a Red synthetic surface.
- Improvements to the long jump landing areas, including new sand and a larger landing area to keep current with safety standards.
- Improvements to the polevault landing areas, including concrete anchorages for the standards and a larger paved area for the landing system to rest on.
- Modifications to the discus cage to keep up with current safety standards.
- Modifications to the Jumping runways and resurfacing.
Sept. 5 - Final Surface Preparation - Lines and Lettering |
Aug. 11 - Rubberized Surface Complete - No Lines Yet |
Aug. 1 - Rubberized Surface First Coat. Discus Cage Completed |
July 14 - New Landing Sand Pits Constructed |
Bituminous Concrete Cures for 28 Days. |
June 20 - Blacktop layed down. |
June 18, 2008 - Crushed stones ready for Bituminous Concrete. Jumping pits dug out. |
June 10, 2008 - Bituminous Concrete Removed and Crushed Stone base improved |
Bituminous Concrete Removed and Discus Cage Stipped for Improvements |
More piles of the old surface |
June 2, 2008 - Work begins !!!!The rubberized surface is stripped to expose the blacktop. |
Crews arrived to strip the old surface from the track. |
Here a piece of the old track is left to show the difference between the track surface and the bare concrete. |
The remains of the track are seen in piles. |